In its June 2014 meeting, the PPC approved
the project to upgrade the Church’s toilet facilities for its parishioners at a
budgetary cost of P764,000. The approved design as shown above was made by
Arch. Ariel Daulat.
The renovation of the existing facilities
started last July 21 and is targeted to be completed on September 12 in time
for its blessing this coming fiesta day. The public toilets will have separate
facilities for men and women, as well as a new one for persons with disability
(PDW). Arch. Daulat was awarded as the main contractor for the project
responsible for the day-to-day management and supply of labor resources for the
construction. It will be the PPC, through the Temporalities Ministry, that will
procure the materials either through direct purchase or from donations from
benevolent sponsors.